Agenda Item Title:
Approve Change Order 1F to Heavy Constructors, Inc., for St Patrick Street Reconstruction - Mt Rushmore Rd to 5th St. Project No. 2582 / CIP No. 51126 for a decrease of $340,318.74.
Origination Group:
Public Works Committee
Origination Meeting Date:
10/15/2024
City Council Hearing Date:
10/21/2024
Staff Contact:
Roger Hall
Location:
St Patrick St - Mt Rushmore Rd to 5th St
Agenda Item Summary:
This is a final change order reconciling final quantities.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
CIP | Drainage |
Enterprise | Water |
Enterprise | Water Reclamation |
Is Funding Budgeted?:
Budgeted