Agenda Item Title:
Authorize Staff To Advertise Bids For Debra Drive Retaining Wall. Project No. 2791/CIP No. 51360. Estimated Cost $300,000.00
Origination Group:
Public Works Committee
Origination Meeting Date:
10/01/2024
City Council Hearing Date:
10/07/2024
Staff Contact:
Sara Odden
Agenda Item Summary:
This project is for the reconstruction of an existing concrete block wall located along the eastern side of Debra Drive, about 4 feet east of the edge of sidewalk. The wall is approximately 150 feet in length and at a height of 3 to 5 feet (the roadway is higher than the adjacent property). This project will replace the existing wall with a block wall, as well as any disturbed sidewalk, curb and gutter, and street items necessary to install the new wall.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
Is Funding Budgeted?:
Budgeted