Agenda Item Title:
Authorize Mayor And Finance Director To Sign Amendment No. 1 To Professional Services Agreement Between The City Of Rapid City And Foth Infrastructure And Environment, LLC, For Elk Vale Lift Station Equipment Improvements. Project No. 2755/CIP No. 51394. Amount Not To Exceed $95,952.00
Origination Group:
Public Works Committee
Origination Meeting Date:
10/01/2024
City Council Hearing Date:
10/07/2024
Staff Contact:
Brandon Quiett
Agenda Item Summary:
During the investigation phase of the project, additional necessary improvements to the lift station were identified, including wet well coatings, a separate equipment pre-procurement bid package, HVAC Improvements to the existing generator building, and additional H2S investigation and design. This amendment also includes construction administration services for the additional design components.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|