Posted: September 06, 2024
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW091024-01

Agenda Item Title:

Approve Change Order 2F To Mainline Contracting, Inc. For Sheridan Lake Rd Breakout Project, Project No. 2736, CIP No. 51122.1, For A Decrease Of $66,810.51.

Origination Group:
Public Works Committee
Origination Meeting Date:
09/10/2024
City Council Hearing Date:
09/16/2024
Staff Contact:
Roger Hall
Agenda Item Summary:
This is a final change order reconciling quantities.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
Is Funding Budgeted?:
Budgeted

Recommendations:

Login Form