Agenda Item Title:
Approve Change Order 2F To Simon Contractors Of SD, Inc., For Sunburst Drive Reconstruction, Project No. 2532, CIP No. 51253, For A Decrease Of $107,400.42.
Origination Group:
Public Works Committee
Origination Meeting Date:
08/27/2024
City Council Hearing Date:
09/03/2024
Staff Contact:
Roger Hall
Agenda Item Summary:
This is a final change order to reconcile quantities.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sewer | Expansion |
Water | Replace/Improve |
CIP | Streets |
CIP | Drainage |
Is Funding Budgeted?:
Budgeted