Posted: August 09, 2024
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW081324-01

Agenda Item Title:

Approve Change Order 3 To Mainline Contracting, Inc., For 143rd & Country Rd, Project No. 2694, CIP No. 51220, For An Increase Of $176,966.64.

Origination Group:
Public Works Committee
Origination Meeting Date:
08/13/2024
City Council Hearing Date:
08/19/2024
Staff Contact:
Roger Hall
Agenda Item Summary:
Field conditions discovered approximately a 715LF section of roadway adjacent to the current project that is need of replacement. This section of roadway was not in the original bid plans and specifications. In addition, two storm sewer culverts were found to be in a condition that is beyond repair, along with a section of a previously unmarked water main that was uncovered during the box culvert excavation. Performing the repairs as a value add in the current project will realize significant cost savings over creation of a separate project to address these concerns.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sewer Replace/Improve
Sewer Expansion
CIP Streets
Grants ARPA
Is Funding Budgeted?:
Budgeted

Recommendations: