Agenda Item Title:
Approve Change Order 3F to Lloyd Construction Company for Parks Greenhouse, Project PR23-6191, for a decrease of $391.05.
Origination Group:
Public Works Committee
Origination Meeting Date:
07/30/2024
City Council Hearing Date:
08/05/2024
Staff Contact:
Melissa Petersen
Agenda Item Summary:
Change order to reflect final quantities – decreases for HVAC equipment hanging that greenhouse install crew performed instead of Midwestern Mechanical and an asphalt patch in the street that the Street Division completed rather than Lloyd; increase to cover building permit fees that Lloyd originally paid (City pays for building permit fees)
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
General Fund | Parks and Rec |
Is Funding Budgeted?:
Budgeted