Agenda Item Title:
Approve Change Order #1 to Simon Contractors of South Dakota, Inc. for Sedivy Lane Sanitary Sewer Improvements, Project No. 2735, CIP No. 51351, for an increase of $38,322.58.
Origination Group:
Public Works Committee
Origination Meeting Date:
03/26/2024
City Council Hearing Date:
04/01/2024
Staff Contact:
Lindsey Martin
Agenda Item Summary:
Due to unforeseen circumstances, large rock and cobbles were observed during auger boring activities that required a different method to complete the work. This resulted in additional time and material and the use of additional equipment.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sewer | Replace/Improve |
CIP | Streets |
Is Funding Budgeted?:
Budgeted