Agenda Item Title:
Approve Change Order 1 to Layne Christensen Company for Well 10 and Well 11 Improvement Project, Project No. 2727, CIP No. 51362, for an increase of $3,284.17.
Origination Group:
Public Works Committee
Origination Meeting Date:
02/13/2024
City Council Hearing Date:
02/20/2024
Staff Contact:
Brandon Quiett
Agenda Item Summary:
This change order extends the completion date of Well 10 to May 31, 2024 and Well 11 to May 3, 2024 due to delayed materials delivery. The additional cost for Well 11 is due to the relocation of the C/T cabinet to accommodate HVAC improvements.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Water | Repalce/Improve |
Is Funding Budgeted?:
Budgeted