Approve Change Order #3 to PKG Contracting, Inc for Miscellaneous Improvements Projects, Facility Type and Fencing Improvements Project# 2608, CIP# 51132.4, for an increase of $161,405.70.
Origination Group:
Public Works Committee
Origination Meeting Date:
02/13/2024
City Council Hearing Date:
02/20/2024
Staff Contact:
Eddie Lopez
Agenda Item Summary:
Change Order #3 will be adding pay items to account for additional work that is required at the Water Reclamation Facility due to unforeseen conditions and repairs to the existing westerly trickling filter.
This change order will also set new project milestone dates to Schedule A, B, C and H due to additional work added and delays in equipment and start up from the suppliers.
Schedule A – Added additional Work, Start up for Flare, Vendor Availability
Schedule B – Start up for Generators, Warranty Work
Schedule C – Motor Warranty Work
Schedule H – Added additional Work, Coordination for Gate Controls
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
ARPA Grant | Water |
ARPA Grant | Wastewater |
Is Funding Budgeted?:
Budgeted