Posted: January 26, 2024
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW013024-15

Agenda Item Title:

Approve Change Order #1 to Lloyd Construction Company for Parks Greenhouse, Project PR23-6191, for an increase of $8,868.59

Origination Group:
Public Works Committee
Origination Meeting Date:
01/30/2024
City Council Hearing Date:
02/05/2024
Staff Contact:
Melissa Petersen
Agenda Item Summary:
While excavating for the footing subgrade, unstable and saturated soils were encountered. In order to provide stability to the greenhouse footings, our engineers determined that further excavation and an additional layer of subgrade aggregate was necessary. Not making this change could have undermined the stability and longevity of the greenhouse structure and floor slab.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Parks and Rec
Is Funding Budgeted?:
Budgeted
Funding Source & Fiscal Impact Notes:
While excavating for the footing subgrade, unstable and saturated soils were encountered. In order to provide stability to the greenhouse footings, our engineers determined that further excavation and an additional layer of subgrade aggregate was necessary. Not making this change could have undermined the stability and longevity of the greenhouse structure and floor slab.

Recommendations:

Login Form