Agenda Item Title:
Approve Change Order #1 to Complete Concrete, Inc. for Sioux Park Tennis Courts Reconstruction, Project PR22-6186, for a decrease of $1,185.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
08/15/2023
City Council Hearing Date:
08/21/2023
Staff Contact:
Melissa Petersen
Agenda Item Summary:
Construction of the Sioux Park Tennis Courts project has uncovered a few areas where changes were determined to be in the best interest of the Department of Parks and Recreation. Change Order #1 addresses three items.
- Quantity reduction of landscape curb caused by VE design changes
- Switching from hydroseed to sod on a slope which drains toward Jimmy Hilton Pool (affects three bid items)
- Refined square footage of windscreen to be purchased, chose a sturdier product than originally specified, and removed contractor install for an overall reduction in cost
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
0107 | 0132 |
0505 | 8912 |
Is Funding Budgeted?:
Budgeted