Agenda Item Title:
Approve Change Order #1F to Iron Horse Excavating, Inc. for Meadowbrook Bank Stabilization, Project PR21-6183, for a decrease of $20,130.70.
Origination Group:
Public Works Committee
Origination Meeting Date:
07/11/2023
City Council Hearing Date:
07/17/2023
Agenda Item Summary:
Work limits were adjusted in the field so final quantities on several items changed leading to a decrease in the overall project cost. Project is finished.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Parks & Rec |
Is Funding Budgeted?:
Budgeted