Agenda Item Title:
Approve Change Order 1 for Fire Station #1 Improvements with MAC Construction Co. Inc. Project No. 2612 / CIP No. 51310 for an Increase of $60,821.52.
Origination Group:
Public Works Committee
Origination Meeting Date:
05/30/2023
City Council Hearing Date:
06/05/2023
Staff Contact:
Rod Johnson
Agenda Item Summary:
Primary change is the Phase 1 Asbestos Abatement and Drilled Pier Casing addition. The known asbestos abatement and demo were removed from the bidding process to allow competitive bidding. The drilled pier casing was removed during the Value Engineering Process and was to be added back on a unit cost basis.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
General Fund | Fire |
Is Funding Budgeted?:
Budgeted