Agenda Item Title:
Approve Change Order #1 to LEi for Robbinsdale Phase 6 Fairlane Drive Reconstruction, Project No. 2518, CIP No. 51232-C, for an increase of $40,981.20.
Origination Group:
Public Works Committee
Origination Meeting Date:
04/25/2023
City Council Hearing Date:
05/01/2023
Staff Contact:
Roger Hall
Agenda Item Summary:
Adjusted for quantities and field conditions.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
CIP | Drainage |
Water | Replace/Improve |
Wasterwater | Replace/Improve |
Is Funding Budgeted?:
Budgeted