Agenda Item Title:
Approve Change Order #5F to Mainline Contracting, Inc. for Elk Vale Lift Station Gravity Main & Force Main Upgrades, Project No. 2480, CIP No. 50729, for a decrease of $1,383.82.
Origination Group:
Public Works Committee
Origination Meeting Date:
04/25/2023
City Council Hearing Date:
05/01/2023
Staff Contact:
Roger Hall
Agenda Item Summary:
This is a final change order reconciling final project quantities.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Wastewater | Replace/Improve |
Is Funding Budgeted?:
Budgeted