Agenda Item Title:
Approve Change Order #1F to Heavy Constructors, Inc. for Knollwood Drainage Basin Detention Element 303, Project# 2601, CIP# 51303, for an increase of $55,994.02.
Origination Group:
Public Works Committee
Origination Meeting Date:
02/28/2023
City Council Hearing Date:
03/06/2023
Staff Contact:
Jordan Adkins
Agenda Item Summary:
This is a final change order to reconcile quantities for project completion. Additional work was required for the storm sewer pipe as the existing pipe at the tie-in points was in disrepair
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Drainage |
Stormwater | Drainage |
Is Funding Budgeted?:
Budgeted