Agenda Item Title:
Authorize Staff to Advertise for Bids for the Meade Street Water Reconstruction – 7th Street to 5th Street, Project No. 21-2679 / CIP 51077. Cost: $740,000
Origination Group:
Public Works Committee
Origination Meeting Date:
12/13/2022
City Council Hearing Date:
12/19/2022
Staff Contact:
Jacob Lauer
Agenda Item Summary:
This project includes the replacement of approximately 1,300 lineal feet of water main in Meade Street from 7th Street to 5th Street and in 6th Street from Flormann Street to Meade Street. The existing 6 inch water main has reached the end of its useful life and needs to be replaced.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Water | Replace/Improve |
CIP | Streets |
Is Funding Budgeted?:
Budgeted