Posted: November 10, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW111522-05

Agenda Item Title:

Approve Change Order #4 to Mainline Contracting, Inc. for Elk Vale Lift Station Gravity Main & Force Main Upgrades, Project# 2480, CIP# 50729, for an increase of $105,880.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
11/15/2022
City Council Hearing Date:
11/21/2022
Staff Contact:
Roger Hall
Agenda Item Summary:
This change order reflects the purchase of domestic fittings at an additional cost to avoid schedule delays due to backordered import fittings as well as the relocation of a street light and the extension of ARV 5, 6, 7 to gain positive drainage.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sanitary Sewer Expansion
Is Funding Budgeted?:
Budgeted

Recommendations:

Attachments & Links to Download:

PW111522-05 Project 2480 CCO #4 ( pdf, 3.69 MB )