Agenda Item Title:
Authorize Staff to Advertise Bids for St. Patrick St. Reconstruction – Mt. Rushmore Rd. to 5th St., Project No. 20-2582 / CIP 51126. Estimated Cost $5,700,000.
Origination Group:
Public Works Committee
Origination Meeting Date:
08/30/2022
City Council Hearing Date:
09/06/2022
Staff Contact:
Sara Odden
Agenda Item Summary:
This project is for the reconstruction of approximately 1,500 linear feet of St. Patrick St from Mt. Rushmore Rd to 5th St. The reconstruction is needed as the existing roadway and underground utilities are nearing the end of their useful life. The project includes new concrete pavement on St. Patrick St and asphalt pavement on the side street connections, curb and gutter, ADA improvements, retaining wall replacement, water main replacement, sanitary sewer main replacement, and storm sewer improvements. A new water main will also be installed in 7th St, from St. Patrick St to St. Andrew St. The traffic signal at the intersection of St. Patrick St and 5th St will be upgraded with new poles, signal heads, a video detection system, and accessible pedestrian push buttons.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
Sanitary Sewer | Improvements |
CIP | Drainage |
Water | Improvements |
Is Funding Budgeted?:
Budgeted