Agenda Item Title:
Approve Change Order #1 to Heavy Constructors, Inc. for Deadwood Ave Reconstruction Phase 1, Project #17-2375, CIP #50437.1, for an increase of $166,632.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
08/30/2022
City Council Hearing Date:
09/06/2022
Staff Contact:
Roger Hall
Agenda Item Summary:
Rock excavation field conditions differed from what was anticipated. The quantity estimates increased from 100 CYS to 2,500 CYS on the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sanitary Sewer | Expansion |
CIP | Streets |
Is Funding Budgeted?:
Budgeted