Agenda Item Summary

Agenda Item Ref. #: PW072622-05

Agenda Item Title:

Approve Change Order #2F to Underground Construction, LLC for St Andrew Street East of Palo Verde Drive Street Reconstruction and Utility Project, Project #20-2604, CIP #51260, for an increase of $27,887.80.

Origination Group:
Public Works Committee
Origination Meeting Date:
07/26/2022
City Council Hearing Date:
08/01/2022
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve Change Order #2F to Underground Construction, LLC for St Andrew Street East of Palo Verde Drive Street Reconstruction and Utility Project , Project #20-2604, CIP #51260, for an increase of $27,887.80 for adjusted to actual quantities, widened construction limited and liquidated damages.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sanitary Sewer Replace/Improve
CIP Streets
Is Funding Budgeted?:
Budgeted

Recommendations: