Agenda Item Title:
Request Authorization for Mayor and Finance Officer to Sign Amendment Number 1 to the Professional Services Agreement with HDR, Inc. for E Anamosa St. – Street and Storm Sewer Repairs, Project No. 21-2639 / CIP No. 51153, in the amount not to exceed $22,825.
Origination Group:
Public Works Committee
Origination Meeting Date:
06/28/2022
City Council Hearing Date:
07/05/2022
Staff Contact:
Brandon Quiett
Agenda Item Summary:
A project to fully replace two storm sewer structures (depth of 35’+) was bid in May 2022. The project received only one bid and was significantly over the engineer’s estimate. The bid was rejected. This amendment is to have HDR redesign the project to reflect a revised scope, increase the constructability, and to re-bid the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
CIP | Drainage |
Is Funding Budgeted?:
Budgeted