Posted: April 22, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW042622-03

Agenda Item Title:

Approve Change Order #1 to Layne Christensen Company Well #9 Pump Replacement, Project No. 20-2573 / CIP No. 51271, for a Contract Time Extension of 30 days.

Origination Group:
Public Works Committee
Origination Meeting Date:
04/26/2022
City Council Hearing Date:
05/02/2022
Staff Contact:
Doug Noyes
Agenda Item Summary:
Work on Well 9 cannot begin until Well 5&6 (Project No. 20-2474) work has been completed. Due to continued supply chain issues that have caused time delays in receiving equipment for the Well 5&6 project, staff is recommending a contract time extension of 30 days.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center

Recommendations:

Attachments & Links to Download:

PW042622-03 Project 2573 CO1 