Agenda Item Title:
Approve Change Order #1 to R.C.S. Construction, Inc. for St. Cloud Street Reconstruction Project – 5th Street to Highland Court, Project No. 19-2487 / CIP No. 51036, for a decrease of $38,386.35.
Origination Group:
Public Works Committee
Origination Meeting Date:
04/26/2022
City Council Hearing Date:
05/02/2022
Staff Contact:
Doug Noyes
Agenda Item Summary:
Prior to awarding the project to the lone bidder, R.C.S. Construction, the City and contractor negotiated pricing in an effort to reduce construction costs. As a result of those negotiations, the completion date(s) for the project have been extended in exchange for a price deduct.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sewer | Replacement |
Water | Replacement |
CIP | Street |
Is Funding Budgeted?:
Budgeted