Posted: April 22, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW042622-02

Agenda Item Title:

Approve Change Order #1 to R.C.S. Construction, Inc. for St. Cloud Street Reconstruction Project – 5th Street to Highland Court, Project No. 19-2487 / CIP No. 51036, for a decrease of $38,386.35.

Origination Group:
Public Works Committee
Origination Meeting Date:
04/26/2022
City Council Hearing Date:
05/02/2022
Staff Contact:
Doug Noyes
Agenda Item Summary:
Prior to awarding the project to the lone bidder, R.C.S. Construction, the City and contractor negotiated pricing in an effort to reduce construction costs. As a result of those negotiations, the completion date(s) for the project have been extended in exchange for a price deduct.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sewer Replacement
Water Replacement
CIP Street
Is Funding Budgeted?:
Budgeted

Recommendations:

Attachments & Links to Download:

PW042622-02 Project 2487 CO1

Login Form