Approve Change Order #3 to Simon Contractors of SD, Inc. for 12th Street Reconstruction – West Main to Fulton Street, Project 19-2499 / CIP No. 50927, for a decrease of $195,439.61.
Origination Group:
Public Works Committee
Origination Meeting Date:
03/29/2022
City Council Hearing Date:
04/04/2022
Staff Contact:
Roger Hall
Agenda Item Summary:
Changes in quantities are associated with the elimination of water and sewer mains, adjustments in surfacing quantities, and water main revisions at South Street.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Water | replacement |
Wastewater | Replacement |
CIP | Streets |
CIP | Drainage |