Posted: March 25, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW032922-04

Agenda Item Title:

Approve Change Order #2 to Simon Contractors of SD, Inc. for 12th Street Reconstruction – West Main to Fulton Street, Project 19-2499 / CIP No. 50927, for an increase of $220,550.43.

Origination Group:
Public Works Committee
Origination Meeting Date:
03/29/2022
City Council Hearing Date:
04/04/2022
Staff Contact:
Roger Hall
Agenda Item Summary:
This change order reconciles work completed in 2021.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Water Replacement
Wastewater Repalcement
CIP Streets
CIP Drainage
Is Funding Budgeted?:
Budgeted

Recommendations:

Attachments & Links to Download:

PW032922-04 Project 2499 CO 2 ( pdf, 3.06 MB )