Agenda Item Title:
Approve correction to Award Recommendation for E Main Street N Bridge Repair, Project No. 19-2525 / CIP No. 51247 awarded at the October 18, 2021 Council Meeting to the lowest responsible bidder, Heavy Constructors, Inc. in the amount of $1,407,815.01. Due to a calculation error, the total bid amount was incorrect and should be $1,407,815.02.
Origination Group:
Public Works Committee
Origination Meeting Date:
03/01/2022
City Council Hearing Date:
03/07/2022
Staff Contact:
Sara Odden
Agenda Item Summary:
The bid award was incorrect due to a calculation error in the contractor’s bid proposal. It was awarded in the amount of $1,407,815.01 and needs to be corrected to $1,407,815.02.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
Is Funding Budgeted?:
Budgeted