Agenda Item Title:
Approve Change Order #1F to Hilt Construction Inc. for 2021 Annual Guardrail Project, Project 21-2672/CIP 51112 for an increase of $2,540.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
11/09/2021
City Council Hearing Date:
11/15/2021
Staff Contact:
Jesse Rieb
Agenda Item Summary:
Approve Change Order #1F to Hilt Construction Inc. for 2021 Annual Guardrail Project, Project 21-2672/CIP 51112 for an increase of $2,540.00. Adjustments made for actual quantities used to complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
CIP | Streets |
Is Funding Budgeted?:
Budgeted