Agenda Item Title:
Approve change order 1 F to Simon Contractors of SD, Inc. for 2020 Street Patching Project, Project #2544/CIP NO.50844 for an increase of $12,636.38.
Origination Group:
Public Works Committee
Origination Meeting Date:
09/15/2020
City Council Hearing Date:
09/21/2020
Agenda Item Summary:
Approve change order 1 F to Simon Contractors of SD, Inc. for 2020 Street Patching Project, Project #2544/CIP NO.50844 for an increase of $12,636.38. Final quantities were adjusted to complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve