Agenda Item Title:
Authorize Mayor and Finance Officer to Sign an Agreement between the City of Rapid City and HDR Engineering, Inc. for E Main Street N Bridge Repair, Project No. 19-2525/CIP No. 51247 in the amount of $124,468.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
06/09/2020
City Council Hearing Date:
06/15/2020
Staff Contact:
Sara Odden
Location:
E Main St N ROW
Agenda Item Summary:
This agreement is for HDR Engineering, Inc. to provide professional services for the design and
bidding for a bridge repair project on the E Main Street N bridge located between Steele Ave and
Brennan Ave. The City of Rapid City was previously awarded 2019 Bridge Improvement Grant
(BIG) funds to cover 75% of the design and construction repair costs on this structure, up to a
maximum of $553,500.00. This project will utilize those funds to complete the design, and subsequent construction of the bridge repairs.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve