Agenda Item Title:
Approve change order 4F to Tru-Form Construction, Inc. for Disk and Haines Avenue Intersection, Project #16-2347/CIP NO.51121 for an increase of $3,016.99.
Origination Group:
Public Works Committee
Origination Meeting Date:
05/12/2020
City Council Hearing Date:
05/18/2020
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve change order 4F to Tru-Form Construction, Inc. for Disk and Haines Avenue Intersection, Project #16-2347/CIP NO.51121 for an increase of $3,016.99. Final quantities were adjusted to complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
604 | 834 |
602 | 933 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve