Agenda Item Title:
Approve Change Order 1 F to Mainline Contracting, Inc. for Fire Hydrant Installation Project, Project #19-2497/CIP 50808 for an increase of $11,842.09.
Origination Group:
Public Works Committee
Origination Meeting Date:
11/26/2019
City Council Hearing Date:
12/02/2019
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve Change Order 1 F to Mainline Contracting, Inc. for Fire Hydrant Installation Project,
Project #19-2497/CIP 50808 for an increase of $11,842.09. Final quantities were adjusted to
complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 934 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve