Agenda Item Title:
Authorize Mayor and Finance Officer to Sign an Agreement between the City of Rapid City and FMG Engineering, Inc. for Wildwood Area Reconstruction Projects, Project No. 19-2504 / CIP No. 51004. In the amount of $393,101.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
10/01/2019
City Council Hearing Date:
10/07/2019
Staff Contact:
Sara Odden
Location:
Wildwood Drive, Una Del Dirve, and Sunburst Drive
Agenda Item Summary:
This agreement is for FMG Engineering to provide professional services for the preliminary design
of three separately bid projects (Sunburst Drive Reconstruction, Project No. 19-2532/CIP 51253;
Una Del Drive Reconstruction, Project No. 192505/CIP 50914; and S. Wildwood Reconstruction
– Phase 2, Project No. 19-2506/CIP 51003). Preliminary design contract will include a conceptual
design for all three projects, as well as recommended project phasing. Upon completion of this
contract, three separate agreements are anticipated to follow, one for each individual project for
final design and bidding services.
Project includes the removal and installation of asphalt roadway surfacing, the reconstruction of
existing water mains and the installation of new sewer mains within the project vicinity. A drainage
analysis will be completed and storm culverts will be installed where necessary. Guardrail will be
installed as required by AASHTO Guidelines for Roadside Safety.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Wastewater Enterprise | Wastewater Expansion |
Water Enterprise | Water/Replacement/Imporvement |
Water Enterprise | Water Expansion |
CIP | Streets |
CIP | Drainage |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve