Agenda Item Title:
Approve Change Order 1 F to Underground Construction, Inc. for 7th Street Water Extension St. Cloud to Franklin St. and St. James Sanitary Sewer Mt. Rushmore Rd to 9th St. Project #18- 2433/CI P 51199 for an increase of $12,891.95.
Origination Group:
Public Works Committee
Origination Meeting Date:
09/10/2019
City Council Hearing Date:
09/16/2019
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve Change Order 1 F to Underground Construction, Inc. for 7th Street Water Extension
St. Cloud to Franklin St. and St. James Sanitary Sewer Mt. Rushmore Rd to 9th St. Project #18-
2433/CI P 51199 for an increase of $12,891.95. Final quantities adjusted to complete the
project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
602 | 933 |
604 | 833 |
602 | 934 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve