Agenda Item Title:
Authorize Mayor and Finance Officer to sign amendment #1 between the City of Rapid City and HDR Engineering, Inc. for Professional Services for Rapid City Water Reclamation Facility Digester MCC and UV/Admin. Transfer Switch Replacement, Project Number: 19 – 2485 / CIP #51216 in the amount of $29,405.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
06/25/2019
City Council Hearing Date:
07/01/2019
Staff Contact:
Stacey Titus
Location:
Water Reclamation Facility
Agenda Item Summary:
The Water Reclamation Facility (WRF) needs to replace the existing Digester Facility MCC as it
has exceeded its’ design life and its’ condition has deteriorated. The UV/Admin. electrical
transfer switch was recently determined to be deficient and in need of replacement too. The
complexity of the proposed electrical system replacements has required an additional level of
effort by the consultant. WRF staff has also identified additional electrical needs that are being
incorporated into the original project. It will be more cost effective to address these items at this
time. Additional design effort has been expended by the Consultant for this reason. As a result
of the complexity of the project, additional Construction effort will be required by the consultant
and is also proposed as part of this amendment.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
604 | 7072 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve