Posted: April 03, 2019
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW040919-02

Agenda Item Title:

Authorize Staff to Seek Proposals for Engineering Services for 12th Street Reconstruction - West Main Street to Fulton Street, Project No. 19-2499 / CIP 50927

Origination Group:
Public Works Committee
Origination Meeting Date:
04/09/2019
City Council Hearing Date:
04/15/2019
Staff Contact:
Brandon Quiett
Location:
12th Street (West Main Street to Fulton Street)
Agenda Item Summary:
Reconstruct water and sewer mains and services, street pavement, and improve drainage within 12th Street from W. Main Street to Fulton Street.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
CIP Drainage
Sewer Replace/Improve
Water Replace/Improve
Stormwater Replace/Improve
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve