Posted: December 07, 2018
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW121118-05

Agenda Item Title:

Authorize Staff to Apply for the 2019 Bridge Improvement Grant (BIG) Funds for Preservation and Repair Work for the East Main Street North Bridge, and to Accept the Funds if Awarded

Origination Group:
Public Works Committee
Origination Meeting Date:
12/11/2018
City Council Hearing Date:
12/17/2018
Staff Contact:
Sara Odden
Agenda Item Summary:
The requested grants would cover 75% of the costs for design, construction and construction administration for the preservation and repair work on the East Main Street North bridge. Approximate project costs are as follows: Total Cost = $591,000. Grant = $441,000. City Match = $150,000

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
CIP Streets
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve