Agenda Item Title:
Approve Change Order 1F to Hills Materials Company for Anamosa Street Reconstruction Midway Street to Milwaukee Street Project, Project #07-1473/CIP 50559 for a decrease of $86,936.23.
Origination Group:
Public Works Committee
Origination Meeting Date:
10/30/2018
City Council Hearing Date:
11/05/2018
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order 1F to Hills Materials Company for Anamosa Street Reconstruction Midway Street to Milwaukee Street Project, Project #07-1473/CIP 50559 for a decrease of $86,936.23. Quantities adjusted to complete project. Project also was not completed on time and incurred 80 days of liquidated damages.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 933 |
604 | 833 |
505 | 89101 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve