Agenda Item Title:
Approve Change Order 1F to Highmark Construction, Inc. for East Rapid City Water System Expansion Mesa View Estates Subdivision, Radar Hill Road and Morris Lane Water Extensions Project, Project #14-2198/CIP 50964.F for a decrease of $50,843.80.
Origination Group:
Public Works Committee
Origination Meeting Date:
10/30/2018
City Council Hearing Date:
11/05/2018
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order 1F to Highmark Construction, Inc. for East Rapid City Water System Expansion Mesa View Estates Subdivision, Radar Hill Road and Morris Lane Water Extensions Project, Project #14-2198/CIP 50964.F for a decrease of $50,843.80. Quantities adjusted to complete project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 934 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve