Agenda Item Title:
Approve Change Order 1F to Mainline Contracting, Inc. for Alley South of Kansas City Street Between 4th St and 2nd St Sanitary Sewer Improvements Project, Project #16-2338/CIP 50827 for a decrease of $10,837.76.
Origination Group:
Public Works Committee
Origination Meeting Date:
09/25/2018
City Council Hearing Date:
10/01/2018
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order 1F to Mainline Contracting, Inc. for Alley South of Kansas City Street Between 4th St and 2nd St Sanitary Sewer Improvements Project, Project #16-2338/CIP 50827 for a decrease of $10,837.76. Actual quantities adjusted to complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
604 | 833 |
Is Funding Budgeted?:
Budgeted