Agenda Item Title:
Approve Change Order 1F to Western Construction, Inc. for Terracita Drive Area Pavement Rehabilitation Project, Project #17-2358/CIP 50549 for a decrease of $54,645.58.
Origination Group:
Public Works Committee
Origination Meeting Date:
09/25/2018
City Council Hearing Date:
10/01/2018
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order 1F to Western Construction, Inc. for Terracita Drive Area Pavement Rehabilitation Project, Project #17-2358/CIP 50549 for a decrease of $54,645.58. Actual quantities adjusted to complete the project. In addition, there were 61 Liquidated Damages days add at a charge of $450.00 per day as the contractor did not complete the project on time.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted