Agenda Item Title:
Approve Change Order 5 to R.C.S. Construction, Inc. for E. Idaho, E. Nevada, Ivy Ave Street and Utility Reconstruction and Meade/Hawthorne Drainage Element 221 Improvements, Project No. 15-2253 / CIP No. 5421.3.1B for an increase of $51,861.81.
Origination Group:
Public Works Committee
Origination Meeting Date:
09/11/2018
City Council Hearing Date:
09/17/2018
Petitioner:
Klare Schroeder
Agenda Item Summary:
Quantities adjusted to perform necessary work on the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8912 |
505 | 8910 |
505 | 8911 |
609 | 7402 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve