Agenda Item Title:
Approve Change Order 1F to AB Contracting, LLC for WRF Process Reliability Improvements, Project No. 16-2342 / CIP No. 51141 for an increase of $3,714.81.
Origination Group:
Public Works Committee
Origination Meeting Date:
05/29/2018
City Council Hearing Date:
06/04/2018
Staff Contact:
Dan Coon
Location:
Water Reclamation Facility
Agenda Item Summary:
Modifications to the piping configuration were required in the south aeration basin to allow installation of the new basin interior walls and provide and install a hand geared trolley for the manual hoist previously provided by the Contractor.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
604 | 833 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve