Agenda Item Title:

Request funding to construct an approximately 1,400 ft. collector street to provide access to a proposed 175 acre residential subdivision located south of Catron Blvd. and east of Wellington Drive. Estimated cost of $1,500,000.

Origination Group:
Public Works Committee
Origination Meeting Date:
03/13/2018
City Council Hearing Date:
03/19/2018
Petitioner:
Dream Design International Inc
Staff Contact:
Dale Tech
Location:
South of Catron Boulevard and East of Wellington Drive.
Agenda Item Summary:
The developers of the proposed South Terrace Subdivision are requesting funding to construct approximately 1400 feet of a collector street to connect the 175 acre subdivision to Catron Boulevard. The connection to Catron Boulevard is a full access intersection which means that right and left handed inbound and outbound vehicle movements are allowed. The collector road is located outside of the boundary of the property owned by the developer and is an off-site improvement necessary to provide adequate access to the development. City Staff met with the developer to discuss the road and informed the developer that this request would be forwarded to the City Council for their consideration for CIP funds. City Staff does not support the use of CIP funds for this project as one or more of the many existing CIP projects that have been identified would have to be cancelled or delayed to fund this project.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Is Funding Budgeted?:
Not Budgeted

Recommendations:

Origination Recommendation Action:
Reject
Origination Recommendation Notes:
City Staff does not believe that this proposed project should supersede any existing projects in the City’s current Capital Improvement Plan.
City Council Options:
Send to CIP Committee for consideration Table the request