Agenda Item Title:
Approve Change Order #1F to R.C.S. Construction, Inc. for Box Elder Drainage Basin Element S113 Improvements, Project No. 12-2032.1 / CIP No. 50934.4 for a decrease of $783.32.
Origination Group:
Public Works Committee
Origination Meeting Date:
11/28/2017
City Council Hearing Date:
12/04/2017
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Approve Change Order #1F to R.C.S. Construction, Inc. for Box Elder Drainage Basin Element S113 Improvements, Project# 12-2032.1 / CIP 50934.4 for a decrease of $783.32.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Drainage | Drainage Improvements |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve