Posted: September 26, 2017
Rapid City
Agenda Item Summary

Agenda Item Ref. #: PW092617-01

Agenda Item Title:

Approve Change Order #1-#7 to Dot Energy for Cell 13, 14, & 17 GCCS Landfill Gas Extension, Project No. 16-2370 for an increase of $46,295.61. Total project cost under original bid amount by $4,389.94.

Origination Group:
Public Works Committee
Origination Meeting Date:
09/26/2017
City Council Hearing Date:
10/02/2017
Staff Contact:
Karl Merbach
Location:
Solid Waste Landfill
Agenda Item Summary:
Due to miscalculations in the plan quantities versus the bid quantities, the Solid Waste Staff has agreed to changes and additions for work to complete the expansion of the landfill gas project. With the difference between the actual quantities installed and the additional materials purchased and kept by the City for future project, the overall project cost was under the original award total by $4,389.94. Original Award $725,100.00 versus final cost $720,710.06.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
7104 4320
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

  pdf Change Order (174 KB)