Agenda Item Title:
Authorize Staff to Advertise for Bids for WRF Process Reliability Improvements, Project No. 16-2342 / CIP No. 51141. Estimated Cost: $981,000.00.
Origination Group:
Public Works Committee
Origination Meeting Date:
05/09/2017
City Council Hearing Date:
05/15/2017
Staff Contact:
Dan Coon
Location:
Water Reclamation Facility
Agenda Item Summary:
Improvements to the Water Reclamation Facility (WRF) Trickling Filter Pump Station, Aeration Basin Selector Wall and RAS Recirculation and Drain Pump. Improvements are focused on increasing the reliability of system processes at the WRF. Improvements were identified in the WRF Facility Plan.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
0604 | 0833 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve