Agenda Item Title:
Approve Change Order #1F to Highmark Inc. for East College Avenue East Custer Street Reconstruction – Milwaukee to Racine, Project No. 14-2211 / CIP No. 50916 for a decrease of $76,866.43.
Origination Group:
Public Works Committee
Origination Meeting Date:
12/13/2016
City Council Hearing Date:
12/19/2016
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Change Order #1F to Highmark Inc. for E. College Ave East Custer Street Reconstruction, Milwaukee to Racine Project #14-2211/CIP #50916 for a decrease of $76,866.43.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Streets | Street Improvements |
Sanitary Sewer | Sanitary Sewer Improvements |
Water | Water Improvements |
Drainage | Drainage Improvements |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action: