Agenda Item Title:
Corrected funding for change Order #2F to Mainline Contracting for Countryside Subdivision Water System Conversion, Project No. 15-2257 / CIP 51086 for a decrease of $24,786.30.
Origination Group:
Public Works Committee
Origination Meeting Date:
11/01/2016
City Council Hearing Date:
11/07/2016
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Corrected funding for change Order #2F to Mainline Contracting for Countryside Subdivision Water System Conversion Project #15-2257/CIP 51086 for a decrease of $24,786.30.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sanitary Sewer | Sanitary Sewer Improvements |
Water | Water Improvements |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve